How to
Preparing a base for a patio
5 min read
How do I prepare the base for a patio?
Excavate to allow for the paving thickness, bedding layer and compacted sub-base; lay a geotextile membrane over soft ground; compact the sub-base in layers; then set a fall of roughly 1:80 away from the house before laying on a full mortar bed.
1. Set out and dig
Mark the area, then dig deep enough for the total build-up: paving thickness, bedding layer and compacted sub-base. Remove topsoil, roots and anything soft. Keep the excavation square and slightly larger than the finished patio.
2. Deal with soft ground
Over clay, made ground or soft spots, a geotextile membrane separates the subsoil from the sub-base and stops the stone punching down over time. It is a cheap step that saves settlement later.
3. Compact in layers
Spread the sub-base in layers of no more than about 100mm and compact each layer with a plate compactor. One thick lift will not compact properly, however long you run the machine over it.
4. Falls and levels
Water must run away from buildings. A fall of about 1:80 across the paving is a common target. Keep finished paving below any damp-proof course and make sure air bricks stay clear.
5. Bedding
Most slabs — especially natural stone and porcelain — should be laid on a full mortar bed, not on five dabs. Spot bedding leaves voids that crack slabs and collect water. Porcelain also needs a primer or slurry to bond to the bed.
6. Jointing and edges
Joint once the bed has set, using a product suited to the paving and joint width. Edges to lawns, borders and driveways need restraint so the paving cannot creep.